RETURN TO
Greetings, Grainger Hall!
With summer break just around the corner, we wanted to end Spring 2026 on a positive note with more progress. The construction team is still hard at work installing the framing and support infrastructure within the existing building. Outside, we are wrapping up the underground mechanical room, which will allow our crane to arrive after commencement. This point will mark the beginning of our Mansukhani Family Atrium (the M) build-out, which will start to gradually appear over the summer months.
As we push forward, this phase will cause some spontaneous noise, but we expect more isolated instances, constrained to the work area. We will continuously monitor any disruption this phase may cause and work closely with the contractor to minimize impact during class times, especially during our week of finals.
To summarize what we can expect, please continue to monitor the progress of this timeline, highlighting major activities to be aware of.
What to Expect
DemolitionPhase 3 of Demolition: Expected to occur during the summer, this phase of demolition will involve blocking off various areas in hallways and department spaces on the second, third, fourth, and fifth floors. This effort will be coordinated through public communication and/or directly with the department affected.
Courtyard Foundations & Buildout
Framing & InfrastructureInterior framing, interior infrastructure, and enclosing the courtyard are underway.
Installation of Interior Framing on the Existing Building
Installation of Interior Infrastructure
Enclosing the Courtyard
Finishes, Furniture, & Equipment (FFE)As we complete framing and infrastructure in each area, the installation of finishes, furniture, and equipment (FFE) will begin to outfit the space for use.
ClosingIndividuals and departments directly impacted by the remodel efforts will be engaged separately as needed. General information and timely updates on the disruption can be found on the Commons. As a resource for any external stakeholders, including progress photos, feel free to share the Badger Blueprint webpage for relevant news and updates.
Please keep an eye out for these newsletters for updates on each major milestone listed in the timeline above.
As always, my colleagues in Facilities and I are here to help if you have any questions. We are looking forward to this next step, and please spread the word!
Thank you,Tim Bent Jr.
The second phase of the first floor remodel—demolition and excavation in the courtyard—is complete! The construction team has now moved to framing and installing support infrastructure. This phase is expected to cause some spontaneous noise, but daily disruption should be limited and temporary. We will continue to monitor for any disruptive noise this phase may cause and work closely with the contractor to minimize impact during peak class times.
DemolitionThe final demolition efforts will involve blocking off various areas in hallways and department spaces on the second, third, fourth, and fifth floors. These efforts will be coordinated through public communication and/or directly with the department affected.
Courtyard Excavation & FoundationsRough excavation is complete. Work will begin for the new mechanical room and foundation. Here’s what to expect in the coming months:
The initial installation of the crane was shifted after further review of logistics and safety. These discussions are ongoing, and we will provide further communication once further direction is given.
Installing utilities to support the buildout (ongoing).
Framing & Infrastructure
Installation of FramingThe top rail of the framing is expected to create vibration as it will be secured directly to the floor above. This will be spontaneous and will quickly move locations as the construction team secures each run.
Floor GrindingThis is a disruptive activity, but we are working with the contractor to schedule this where it has the least impact.
Installation of Infrastructure
We are coordinating this work for spring break and will send further communication as we get closer to that timeframe.
Enclosure of the CourtyardSetting structural steel beams, installation of the steel frame for the new grand staircase, and securing steel to the existing building. These are disruptive activities, but we are working with the contractor to schedule them where they have the least impact.
Finishes, Furniture, & EquipmentOnce framing and infrastructure are complete, the installation of finishes, furniture, and equipment (FFE) will begin, outfitting the space for use.
General information, progress photos, and timely updates can be found on the Badger Blueprint webpage. All urgent messages regarding disruption will be posted on the myBiz blog.
Please keep an eye out for these newsletters at the end of each major milestone listed in the timeline above.
Welcome back from winter break! We are making great progress with demolition, advancing us closer to framing, which is set to begin later this spring. Once again, we anticipate that the end of the demolition phase will cause the most disruption, but we will continue to work closely with the contractor to minimize impact during class times.
Demolition
Phase 2The construction team is currently working through this phase of demolition to remove all existing walls & infrastructure, making way for the new build. A few things to note:
Phase 3This phase of demolition will involve blocking off various areas in hallways and department spaces on the second, third, fourth, and fifth floors. This effort will be coordinated through public communication and/or directly with the department affected.
Courtyard Excavation & FoundationsExcavation is nearing completion, which places us into digging the mechanical room and laying out the new foundations. What we can expect in the coming months:
Framing and InfrastructureEnclosing the courtyard, interior framing, and interior infrastructure is expected to begin between March–April 2026.
Individuals and departments directly impacted by the remodel efforts will be engaged separately as needed. General information and timely updates on the disruption can be found on the Commons. As a resource for any external stakeholders, including progress photos, please feel free to share the Badger Blueprint webpage for relevant news and updates.
As always, my colleagues in Facilities and I are here to help if you have any questions. We invite you to share this bulletin with colleagues and partners visiting Grainger Hall for their awareness.
Construction preparations are nearing a close, and we are officially moving into the larger portion of demolition! This phase will remove all existing fixtures, framing, and infrastructure, and begin the excavation of our courtyard. It is anticipated that this phase will cause the most disruption, but we will work closely with the contractor to minimize any major activities during class times.
Construction BeginsWe are nearing the end of setup, but there are a few efforts still in the works:
The first phase of demolition will see the water wall and surrounding areas demolished to prepare for the shutdown of the first-floor east wing. This work is expected to be complete by Nov. 21.
The second phase of demolition, which involves the entire east wing of the first floor, will be blocked off and remain closed until the end of construction.
Finishing the week of Nov. 10 & Nov. 17:
STATUS UPDATE Starting the week of Nov. 24:
Courtyard Excavation & FoundationsThe courtyard will be blocked, allowing heavy machinery to excavate and prepare the footings for our new structure.
Mass excavation is set to begin in December, which includes:
Framing and InfrastructureDemolition, excavation, and foundation work are expected to be completed between March and April 2026. This will lead us into the installation of our new interior framing, interior infrastructure, and enclosing the courtyard.
Individuals and departments directly impacted by the remodel efforts will be engaged separately as needed. General information and timely updates on the disruption can be found on the Commons. As a resource for any external stakeholders, please feel free to share the Badger Blueprint webpage for relevant news and updates.
We are delighted to announce that the first-floor remodel will formally begin on Monday, October 20th! This initial mobilization will involve some amount of setup before we start to hear the familiar noise of heavy equipment and power tools.
To summarize what we can expect, we have put together a timeline and highlighted some major activities within this initial phase to be mindful of.
Anticipated Construction TimelineThe timeline and/or milestones are subject to change.
Transportation
Temporary Environmental SignageThere will be temporary building signage to redirect and inform patron traffic that will go up in October and November.
Demolition Barriers
The first phase of demolition will block off the water wall and surrounding areas from October to November. During this time, all spaces within this area will be demolished. Aside from this barrier, all other patron traffic will remain unchanged during this process.
The second phase of demolition will block off the entire first floor east wing starting in November until the end of construction. See this map with anticipated closures.
DemolitionDemolition of all existing fixtures, framing, and infrastructure will begin in November and likely last through February. In addition, the courtyard excavation will see the same timeline.
Individuals and departments who are directly impacted by the efforts of this remodel will be engaged separately as needed, but general information and/or timely updates on the disruption can be found on the Commons Badger Blueprint Page. As a resource for any external stakeholders, please feel free to share this link for relevant news and updates.
Please keep a lookout for these newsletters at the end of each major milestone listed above in the timeline.
As always, my colleagues in Facilities and I are here if you have any questions, and I hope you are as excited as we are!
Your session has expired. You are being logged out.